Question:
Referring to ISO 9001:2008 clause 7.4.3, Verification of Purchased Product; since we are only a trading company that recieves a limited amount of purchased items at our site, please advise if this requirement is applicable to our organization. Thank You, Razif
Reply:
Hello Razif,
Thanks for contacting us. Regarding ISO 9001:2008, clause 7.4.3, verification of purchased product requirements; it’s important to remember the primary ...
Read More
Uncategorized
Tools for Auditing ISO 9001: 2015, Risk Based Thinking
Inquiry:
Question received via ASQ's Ask the Experts Blog, Published 10/21/2015
In addressing clause 4 of ISO 9001:2015 regarding organization context and interested parties, what type of tool (spreadsheet,diagram,flowchart,etc), would you recommend to use to simplify the practice and to give a proper understanding for auditors? I understand that risk evaluation (ISO 9001:2015) should be accomplished not only at a high level of establishing ...
Read More
When Will ISO 9001:2015 Certifications Start To Be Issued?
Inquiry: Our company currently holds dual certifications to API Q1 and ISO 9001:2008 that are not set to expire until November 2017. When making the transition to ISO 9001:2015 and re-certifying in November 2017, will we be able to do dual certifications or will we have to do API Q1 separate from ISO 9001:2015?
Thanks! Brian
Reply: Hello Brian, in response to your inquiry, the timing for transitioning your existing QMS from ISO 9001:2008 ...
Read More
API Q1, Risk Management, Contingency Planning & MOC
In the event of changes that affect the QMS or organizational structure, does API Q1 require a corrective/preventive action to be initiated to document the MOC action?
Inquiry:
Hi Bill,
Firstly, going through the different queries on this site has been very helpful and greatly appreciated, that being said, I have still been in the grey about the whole MOC process. I know that a change in the QMS or organization structure will initiate an MOC ...
Read More
API Q1, Risk Assessment Requirement
QUESTION:
From: Yusri
Sent: Aug. 12, 2014
To: Q-Blog, Ask the Experts
Subject: API Q1, clause 5.3, Risk Assessment Requirements
Yusri asks the following questions about API Q1:
API Q1, requires the organization to maintain a documented procedure for risk assessment and management. What parameters need to be considered for determining risk and their impact on delivery and quality of product? Should the risk assessment be performed before ...
Read More
API Q1, 9th Edition – Critical Supplier
QUESTION:
From: Joe St. J.,
Sent: May 1, 2014
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 9th Edition, Critical Suppliers
Joe St. J, asks the following about APIQ1:
Hello,
Our company remains in the process of transitioning to API Q1, 9th edition.
While reading sections 5.6.1.2 and 5.6.1.3, one of our suppliers we purchased materials from for our final product that some of his products we deem as "critical" for our final product ...
Read More
API Q1, 9th Edition – Verification of Proprietary Product vs. Receiving Inspection
Muhammad I. asked the following question:
API Q1, 9th edition, clause 5.6.1.2, Section b) and Sub-section iii) requires the organization to verify that supplied product conform to stated requirements when limited by proprietary, legal and/or contractual arrangements.
How is this requirement different from - API Q1, 9th edition, clause 5.6.3, which states that “The organization shall ensure and provide evidence that purchased product and ...
Read More
API Q1, 9th Ed., Quality Policy vs. Objectives
QUESTION:
From: T.S. , Tercel Oilfield
Sent: Jan. 20, 2014
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 9th Ed., Quality policy and Objectives
Am I correct in saying that Objectives should establish the highest overall expectation and direction of the Top Management and that S.M.A.R.T. Goals should then established by the different departments and personnel that are in support of achievement of the Objective?
For instance, each ...
Read More
API 6A and API Q1, 9th Ed., Design – Development
QUESTION:
From:Haseeb Ahmed
Sent: August 28, 2013
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 8th & 9th Ed., Design and Development
If an organization applies for exclusion for Design and Development for following API 6A equipment which are included in its scope:
1. Trees and Crosses
2. Adapters and Spacers
3. Flanged Connectors
Can the Licensee still monogram this equipment based on API 6A?
RESPONSE:
From: Bill ...
Read More