QUESTION:
From: Darcy K.
Sent: May 10, 2014
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 9th edition, Risks, Contingency Plans and MOC
In regard to MOC Process, in your opinion, would it be effective to tie this into corrective and preventative actions? Any corrective or preventative actions that require changes to the QMS also require MOC, and risk assessment as well and furthermore, tying in any contingency plans that require QMS ...
Read More
QMS Requirements
API Q1, 9th Edition – Critical Supplier
QUESTION:
From: Joe St. J.,
Sent: May 1, 2014
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 9th Edition, Critical Suppliers
Joe St. J, asks the following about APIQ1:
Hello,
Our company remains in the process of transitioning to API Q1, 9th edition.
While reading sections 5.6.1.2 and 5.6.1.3, one of our suppliers we purchased materials from for our final product that some of his products we deem as "critical" for our final product ...
Read More
API Q1, 9th Ed., Quality Policy vs. Objectives
QUESTION:
From: T.S. , Tercel Oilfield
Sent: Jan. 20, 2014
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 9th Ed., Quality policy and Objectives
Am I correct in saying that Objectives should establish the highest overall expectation and direction of the Top Management and that S.M.A.R.T. Goals should then established by the different departments and personnel that are in support of achievement of the Objective?
For instance, each ...
Read More
Monitoring & Measurement of Product
QUESTION:
From: ASQ ATE
Sent: Jan. 28, 2014
To: ATCS - QBlog, Ask The Experts
Subject: ISO 9001:2008 and API Q1, 8th & 9th Ed., Monitoring Measurements & Improvement
ISO 9001:2008 states in 8.2.4 Monitoring and measurement of product: "Evidence of conformity with the acceptance criteria shall be maintained." When our plan identifies periodic inspections, variable or attribute, are performed, how can we show evidence without ...
Read More
API Q1, 9th Ed, Control production and Servicing
From: Fayyez Ahmed
Company: DATA Steel Pipes Industries (pvt) Ltd., Punjab,Pakistan
Sent: Sept. 24, 2013
To: ATCS – QBlog, Ask The Experts
Subject: API Q1, 9th Ed., Production and Servicing Procedures
Question: API Q1 9th edition requires control of production and servicing requirements separately under clause reference # 5.7.1.1 & 5.7.1.2. Whereas in API Q1, 8th edition the "Control of production and service provision" was jointly ...
Read More
API Q1, 9th Edition, Management of Change
ATCS – QBLOG, ASK THE EXPERT – September 14, 2013
QUESTION:
From: Muhammad Irhad
Company: EPC Services, Edmonton Alberta
Sent: August 23, 2013
To: ATCS - QBlog, Ask The Experts
Subject: API Q1, 9th Edition - Management of Change (MOC)
I have the following questions regarding API Q1, 9th Edition and its requirement for MOC.
What would be a typical MOC process?
Do we need a documented procedure for MOC process?
MOC ...
Read More